Hello,

tried allot to get my master data over from cProject to ERP-PS ... but still fail. Data in Question would be responsible cost center, responsible person, Customer / Solt to party.

All BADI's seem to have a limited scope of fields to be changed, such as company code etc. I however would like to fill basically all WBS fields ... just miss the point where to do that:

GCC_PS_PROJECT_LABEL = Limited Schope?

All PS user exits or BADI's allow almost no change at all

Substitution (after deactivating master data lock) -> Leads to error - conflict in update

best idea in the moment would be BADI IAOM_ATTRIBUTES, which is suppose to work with structure BAPI_BUS2054_DETAIL - but regardless how I fill c_object_attributes table -> nothing is updated.

Anybody any idea? Would be very much appreciated, thanks, Hans

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Implementing BADI iaom_attributes should be enough, as you mentionned. Did you follow the BADI documentation to implement it?

Have you checked in the ERP in the Controlling Cockpit (COCPCPR) the logs in order to get the root cause of the non integration? (could be some PS validation rules for instance).