on 11-24-2011 5:10 PM
Hi Guru's,
I am in middle of implementing Charm process in solution manager. After importing the logical components into the maintenance project, when i'm creating the IMG project for Dev system in IMG Projecct tab i'm getting below error ...
S:NUMBER_GET_NEXT AEND:000 G INTERVAL_MISSING
Message no. NUMBER_GET_NEXT AEND000
Please help ASAP.
Regards,
Vinod
Please check SNRO setting in the right client. Please refer the note Note 659573 - CD: Number range object/interval AENDBELEG is missing. If you still face the issue, please post further.
Regards,
Rajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
could you please check in the client where the IMG-Project should be
created whether there exists the number range for Object 'AENDBELEG'
in transaction SNRO?
If not, please define the following interval:
Interval No. 01
from 0000000001
to 9999999999
internal number assignment
Regards,
Vincent
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.