on 11-24-2011 4:55 AM
Hi All,
scenario1:if i have 1 class A background work process,and two normal background work processes,if i schedule 3 class C jobs,three will start or only two will be served?
scenario2:if i have 3 normal background(nt reserved for class A) workprocesses,and if i schedule 1 class A and three class C jobs,which will start first?
thanks in Advance.
Hi,
scenario1:if i have 1 class A background work process,and two normal background work processes,if i schedule 3 class C jobs,three will start or only two will be served?
Only 2 of the Class C jobs will start since 1 workprocess is reserved for Class A job.
scenario2:if i have 3 normal background(nt reserved for class A) workprocesses,and if i schedule 1 class A and three class C jobs,which will start first?
1 Class A job will start and 2 Class C jobs will start. Since Class A has priority over Class C jobs.
Hope this helps.
Regards,
Deepak Kori
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
83 | |
10 | |
10 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.