Can someone throw light on how to configure PS RA Key to make the system calculate revenue based on POC percentage of completion. Need specifics around the valuation method and the overall scheme.
Thanks
Hi sridhar,
I am putting very short you need read lot of help for more information.
1 okg1 create new key
2 okg2 version 0 (will be there) turn extended control on and technical cost elements give a single cost element for the fields cost element category 31 RA. tick the indicator transfer to financial accounting.
3 maintain the combination Ra version and Ra key and select the 03 method cost based poc method.
4 maintain line id for costs, revenues
5 in okg5 assign all the cost elements to line id costs,
revenue elements to the line id revenues
6 in okg4 assign the cost line id to k and revenue line id to revenue category.
update the line id to cost elements
7 define the posting rules for cosr ans wipr rucr.
please include the cost element in your allocation structure or else it will throw you a error at the time of settlement.
I tried put it very simple, But it requires lot of reading the sap help to understand in detail.
Thanking you
Vengaiah Chowdary
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Well this topic ofenebling revenue recognition cannot be answered over forum in a simple manner. It does require an elaborate procedure, to get this done. There is more to understand the concept and various business scenario, before one can provide a solution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.