on 11-22-2011 12:38 PM
Hi Group,
I am facing an issue in the Transaction CS03 while displaying the EXTRAS->MORE->Parameter Eff Value Assignment as under:
we have created a set of BOM items on the previous data(21.11.2011) with a different Changed documents for the two BOM items. when we checked the same in CS03 with the Effectivity 'Serial no' , Date (as today - 22.11.2011) and Material as Main material, the System is throwing a message 'No items are valid on 22.11.2011) and when I checked with the same using the Current date(22.11.2011), the BOM items are getting displayed correctly.
Now the requirement is that, the User should be able to see the BOM item details(irrespective of the dates) using the Serial number created in the Change document number for the BOM items.
Kindly provide inputs ASAP.
Thanks in advance for your help.
Regards,
Vishnu
Resolved myself
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Group,
I resolved the Issue myself by managing to populate leading zeros for the Serial Number while creating the Change document number and it resolved the issue.
thanks for your help.
Regards,
Vishnu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.