on 11-22-2011 6:52 AM
Hi experts,
I am implementing PS for Asset procurement, in this i will procure material against material component which is added in Internal activity. I am using scheduling also. Now My client requirement is that he want project progress report on cost basic.
I am using CJ40, CJ30 and CJ32.
IN IMG i have configured like given below
1. I have created Progress version 100
EV base - Cost Plan ( active Proejct, Annual Value)
POC weighting - Weight
Planning type - Basic dates
Early/Late - Earliest Possible
Actual method and Ref plan method tick.
2. Measurement method -
for cost based report i have selected - Cost proportional
3. Default value for measuremnt method -
100 -WBS element - Plan - Cost proportional
100 - WBS element - Actual - Cost proportional
100 - Acitvity ( int)- Actual - Cost proportional
100 - Acitvity ( int)- Actual - Cost proportional
I have put this in CJ20N. I followed following steps
1. CNE1
2. CNE5
but it is showing 0 value in all tabs such as Aggregate planned percentage of completion, Non-aggregated planned percentage of completion
can anyone tell me the total process to get this report perfectly. It is very urgent need so please help me guys.
Thanks,
Thanks for the reply. i am doing same thing but still same problem is there. Can you please tell me how to send you screen shot for this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No i don't have access to 800 client. Give the setting for 132 version so that same thing i can configure and check where i made mistake.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1) in wbs goto progress tab for enter version plan ,give ur method and actual also give your method poc weightage give 1
2) in activity go to progress tab enter your version, give your method for plan and actual give the work measurement method and weightage give 1
3) now confirm the activities if partial confirmation enter the degree of processing (%).
4) goto progress calculation screen and give your project number and select with hierachy and with orders. enter the month and year.
5) excute,
6) goto the report and check the report.
if still not working send screen shot of the report.
Thanking you
Vengaiah Chowdary
Yes i have maintained progress version in each activity tab. i am also seaching for answer please help to get this report correct.
Or just tell me the configuration steps once again i will check this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for Quick reply.
I have changed the setting as per your suggestion. But still error is there.
If you have good docuemnt please send me the link for that.
Please suggest other solution if you have.
Thanks PS gurus.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For activity we need to use degree of processing (work method). measurment method. Then calculate the progress analysis.
Thanking you
Vengaiah Chowdary
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.