Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Error in Project Progress Config and process steps

Hi experts,

I am implementing PS for Asset procurement, in this i will procure material against material component which is added in Internal activity. I am using scheduling also. Now My client requirement is that he want project progress report on cost basic.

I am using CJ40, CJ30 and CJ32.

IN IMG i have configured like given below

1. I have created Progress version 100

EV base - Cost Plan ( active Proejct, Annual Value)

POC weighting - Weight

Planning type - Basic dates

Early/Late - Earliest Possible

Actual method and Ref plan method tick.

2. Measurement method -

for cost based report i have selected - Cost proportional

3. Default value for measuremnt method -

100 -WBS element - Plan - Cost proportional

100 - WBS element - Actual - Cost proportional

100 - Acitvity ( int)- Actual - Cost proportional

100 - Acitvity ( int)- Actual - Cost proportional

I have put this in CJ20N. I followed following steps

1. CNE1

2. CNE5

but it is showing 0 value in all tabs such as Aggregate planned percentage of completion, Non-aggregated planned percentage of completion

can anyone tell me the total process to get this report perfectly. It is very urgent need so please help me guys.

Thanks,

Former Member
Not what you were looking for? View more on this topic or Ask a question