Error in Project Progress Config and process steps

Former Member
0 Kudos

Hi experts,

I am implementing PS for Asset procurement, in this i will procure material against material component which is added in Internal activity. I am using scheduling also. Now My client requirement is that he want project progress report on cost basic.

I am using CJ40, CJ30 and CJ32.

IN IMG i have configured like given below

1. I have created Progress version 100

EV base - Cost Plan ( active Proejct, Annual Value)

POC weighting - Weight

Planning type - Basic dates

Early/Late - Earliest Possible

Actual method and Ref plan method tick.

2. Measurement method -

for cost based report i have selected - Cost proportional

3. Default value for measuremnt method -

100 -WBS element - Plan - Cost proportional

100 - WBS element - Actual - Cost proportional

100 - Acitvity ( int)- Actual - Cost proportional

100 - Acitvity ( int)- Actual - Cost proportional

I have put this in CJ20N. I followed following steps

1. CNE1

2. CNE5

but it is showing 0 value in all tabs such as Aggregate planned percentage of completion, Non-aggregated planned percentage of completion

can anyone tell me the total process to get this report perfectly. It is very urgent need so please help me guys.

Thanks,

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Thanks for the reply. i am doing same thing but still same problem is there. Can you please tell me how to send you screen shot for this.

former_member388328
Active Contributor
0 Kudos

Hi,

Please post it to document sharing sites.

And tell what are the steps you have carried.

Thanking you

Vengaiah Chowdary

Former Member
0 Kudos

No i don't have access to 800 client. Give the setting for 132 version so that same thing i can configure and check where i made mistake.

former_member388328
Active Contributor
0 Kudos

Hi,

1) in wbs goto progress tab for enter version plan ,give ur method and actual also give your method poc weightage give 1

2) in activity go to progress tab enter your version, give your method for plan and actual give the work measurement method and weightage give 1

3) now confirm the activities if partial confirmation enter the degree of processing (%).

4) goto progress calculation screen and give your project number and select with hierachy and with orders. enter the month and year.

5) excute,

6) goto the report and check the report.

if still not working send screen shot of the report.

Thanking you

Vengaiah Chowdary

Former Member
0 Kudos

Yes i have maintained progress version in each activity tab. i am also seaching for answer please help to get this report correct.

Or just tell me the configuration steps once again i will check this.

former_member388328
Active Contributor
0 Kudos

Hi,

If you access to client 800. Please check version 132. and run your senario there, then lot of your doubts will be cleared.

Thanking you

Vengaiah Chowdary

Former Member
0 Kudos

Thanks for Quick reply.

I have changed the setting as per your suggestion. But still error is there.

If you have good docuemnt please send me the link for that.

Please suggest other solution if you have.

Thanks PS gurus.

former_member230675
Active Contributor
0 Kudos

did you maintain the Progress version for each activity in the project progress tab?

former_member388328
Active Contributor
0 Kudos

Hi,

For activity we need to use degree of processing (work method). measurment method. Then calculate the progress analysis.

Thanking you

Vengaiah Chowdary