Hi, our client wants to implement SRM 7.02 with PPS and Plan Driven Procurement. The issue here is that we need from an accepted quotation ( bid response) in srm create follow on document ( as purchase order and contracts) at the backend system (ERP).
I know that PPS works with Extended classic scenario, but I want to know if there´ s a possibility implementing any badi in order to manage the purchase orders or contracts in ERP?
Thanks for your help
Best regards
Liam
Hello,
The only badi available to switch between scenarios is BBP_EXTLOCALPO_BADI.
However, once you switch to classic scenario, PPS will not be valid anymore.
Since the main difference between classic and extended classic is the local PO creation in SRM (lead PO), I guess this functionality that you are looking for is not supported.
Regards,
Ricardo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.