Action canceld Message is coming while asigning resource to WBS element

Former Member
0 Kudos

Hi experts,

when i tried to assign resource to WBS element , it is not allowing me & getting the message "ACTION CANCELLED".

Can you please suggest me the posible solution.

Thanks and Regards,

Mahesh.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Mahesh,

Are you trying to create a Project Team for the WBS element? Which transaction are you running to assign the resource to the WBS element? Provide the details of the error message to suggest a possible solution.

Regards,

Gokul

Former Member
0 Kudos

Hi Gokul,

Thanks for reply.

In project builder i select WBS element> Edit-> WBS element-->Project team for WBS element.

there i am trying to assign resource.

actually i am getting Action Cancelled information (its not an error or warning).and then its not allowing me to assign resource.