on 11-19-2011 4:57 AM
can any body guide which scenario we used for inspection point functionality like while we are configure inspection point in fields tab we found No.insp.points for char.summarized and one check box last inspected sample is valid is there in which requirement we will use this fields and checkbox
Dear,
The Inspection point completion field at the operation level of the task list determines whether the inspection point completion should occur manually or automatically. An automatic valuation of inspection points occurs on the basis of the settings in Customizing. With a manual valuation, the system displays a dialog box in which you valuate the results and confirm the inspection points after you have closed all inspection characteristics.
With a manual completion of inspection points, you must confirm the inspection point data when you save the inspection results. The screen for confirming the data is displayed automatically once all characteristics for the operation have been closed and if inspection point data has been recorded yet.
http://help.sap.com/saphelp_470/helpdata/en/18/4386c0449011d189420000e829fbbd/content.htm
With regards,
Ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank You very much In your Input
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
that field is used to inspect the limited characterstics accrding to your requirement and Indicator is used to valid the last inspection point data and rejected the previously recorded inspection point data in same lot.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.