HI,

We are doing EHP upgrade.we have created a new development environment RS1which will be used for future development till we upgrade the production.We have old development RD1 which is my domain controller want to stop all the transport going out of RD1.As I will be upgrading it and due to higher patch level i want to avoid transport going out.

How can I do that.Changing the client setting wont help as there are users who have access to it and can change it.

Is there any alternate available?

Regard!!

Ravi

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member188883
Active Contributor
0 Kudos

Hi,

Before you start the upgrade, remove that system from transport route. Re-createa a single system transport route for ED1.

You can think of configuring RS1 as new development system and domain controller and configure QAS and PRD with RS1 into a new transport route.

Regards,