costing in WBS bom

Former Member
0 Kudos

Hi All,

I am using a WBS bom in project. I do the cost estimate in CKw1 and also activate it in CKW4. Now this new cost has to appear when I do a network costing. I tried changing the valuation variant but somehow it did not help. The system is still taking the old material master price. Do i need an exit to have the new price for this material and WBS combination.

Any help in this reagrds is appreciated. Also would like to know the transaction to delete this costing run.

Accepted Solutions (0)

Answers (1)

Answers (1)

srinivasa_maruvada
Active Contributor
0 Kudos

Did you do CK24 (Price Update Release and Marking)after CKW1/CKW4?

CK44 - Delete Costing Run

CKR1 Delete Std Cost Estimate

Former Member
0 Kudos

Please review OSS Note 1507600.