Hi Guru's,

The Issue is while creating PO/STO, i am getting the error Customer PLCN35 doesnt exist (please change the entry in Plant )

i will tell you configuration , the vendor Plcn33, having the Plant CN33 and the plant CN33 is having the customer no Plcn33, but the requirement is the recieving should be CN35 , so while creating the PO with recieving pant CN35 , we are getting the error" Customer PLcn35 doesnt exist (Please change the entry in Plant Cn35), is there any way to create PO without changing the Customer in Plant.

Regards,

Dil

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hey Dil,

FYI, WHILE DOING STO THAT PLANT SETTING IS THE 1STEP AS YOU MENTIONED THERE SHOULD BE ONE SUPPLYING PLANT AND RECEIVING PLANT, BOTH THE PLANTS ARE ACTING LIKE CUSTOMER/VENDOR SO WE NEED TO ASSIGN THIS CUSTOMER OR VENDOR IN THE PLANT SETTING .

THE CUSTOMER(PLcn35) WHICH YOU ASSIGNED FOR RECEIVING PLANT,CHECK CUSTOMER MASTER(XD02/03) SALES AREA DATA THE DELIVERING PLANT IS MAINTAINED AS(Cn35) or not if it is not maintained please maintain it and try.

PLEASE CHECK AND REVERT.