Hi Experts,

We're trying to find a way that during creation of Material Reservations from PS, it can already be defined if the Stock should be coming from Plant Stock or Project Stock.

Is there a standard way (or even an Exit) to define during Resrvation creation that Movement Type be 281Q (GI for Network from Project Stock)?

Cheers,

Joed

Accepted Solutions (0)

Answers (1)

Answers (1)

pradeep_mahamuni
Contributor
0 Kudos

Hi,

Check your procurement indicator setting in OPS8 where you define the priorities for the stock. Define priority 1 for the project Check the settings for movement types maintained in OPT1 for the Project stock, 281 is required for GI project.

then system will consider this movement type 281 Q.

Former Member
0 Kudos

Hi Pradeep,

Thanks for the Helpful reply.

However the default WBSE for the source of the Project Stock is always its Superior WBSE. We were on the procedure that it will come from another WBSE outside its tree.

Thanks!

Joed

pradeep_mahamuni
Contributor
0 Kudos

Hi,

If you were planning to take stock from another WBS then first you have to do stock transfer to the WBS for which you are making reservation.

Material will be issue against the Reservation only to the assigned WBS / netwotk .