I need your help in below issue.

We are in SRM 5.0, using classic scneraio.

Internal notes or Vendor text entered in the shopping cart is getting transfered to the text of PR item. But is it not getting copied over to the R/3 PR.

What should I do to copy these texts to R/3 PR?

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi dear,

This is the standard. Using Extended Classic Scenario the SRM document will be the lead document and not all information will be transferred to ECC. This mean, internal note and vendor text can be read in SRM only.

Thank you!