former_member182449
Participant
0 Kudos

Dear Expert,

I have this issue regarding SNP Optimizer ...

I have Demand from Distribution Center 2014

two Production location are available to produce 2013, 2015

Capacity not available for location 2013 , but still the (cost - Effective)

When i Run Optimizer the APO choose location 2013 even with none available capacity

Pleaase note that in optimizer profile i mark "Production Capacity " as constraint

How i can let the system choose the other location 2015 in this case ?

Thanks

Rami

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

hi,

when u mentioned 'E' that itself says, it is inhouse produced.

I was checking if the procurment type is 'X' and can be subcontracted.

Regards,

Sandeep

former_member182449
Participant
0 Kudos

Hi,

No it Can't With Procurment Type X

Regards

Rami

Former Member
0 Kudos

hi,

just checking,

there are no procurement options on 2013 right?

because it might be cost effective to procure from outside than to produce at 2015.

Regards,

Sandeep

former_member182449
Participant
0 Kudos

Hi ,

Thanks for your Response ....

What do you mean by Procurment option ? If you mean Procurment Type it's "E" for both location

Regards

Rami

m_manimaran
Active Contributor
0 Kudos

Hi,

Increase the cost of delay so that the optimizer will choose the other location 2015.

Regards,

Manimaran M.

former_member182449
Participant
0 Kudos

Hi,

I try this way but not working

Regards

Rami

m_manimaran
Active Contributor
0 Kudos

Hi,

May I know, what is the total cost calculated by the optimizer? Please analyze the optimizer log and find out the total cost incurred by producing the material in 2013 eventhough it is delayed. Based on this analysis, increase or adjust your production cost and delay cost at your all locations. For example, increase the delay cost at DC and reduce the production cost at 2015.

Regards,

Manimaran M.

Mrinal_K_Roy
Active Contributor
0 Kudos

Hi ,

Suggest to check the weightage in SNP Profile of cost multipliers so that it is not nil.

Regards,

Mrinal

former_member182449
Participant
0 Kudos

Hi Mrinal,

Please can you give me more details for how i can do that by cost profile ?

Appreciate your Help

Rami

Former Member
0 Kudos

Hi,

Apart from the points mentioned earlier, pls check the following.

1. Have you maintained extended capacity in resource master? Is the resource created as SNP Bucket resource? Pls check the resource master correctly

2. When a planned order is created in this case, does it attach the correct PPM?

3. In the transaction /sapapo/mvm, have you clicked the check box for 'No planned orders without source of supply' ?

Regards

Manotosh