SNP Optimizer

Dear Expert,

I have this issue regarding SNP Optimizer ...

I have Demand from Distribution Center 2014

two Production location are available to produce 2013, 2015

Capacity not available for location 2013 , but still the (cost - Effective)

When i Run Optimizer the APO choose location 2013 even with none available capacity

Pleaase note that in optimizer profile i mark "Production Capacity " as constraint

How i can let the system choose the other location 2015 in this case ?

Thanks

Rami