Hi Experts,

when I create a sales order with 'Plant A' then only two Requirement types are visible.

and when I select "Plant B" total 10 requiirements types are visible.

Can you please guide where do we maintain settings for Plant and allowed requirement types.

Thanks,

Nitin

Accepted Solutions (1)

Accepted Solutions (1)

Shiva_Ram
Active Contributor
0 Kudos

Check the path SPRO->Production ->production planning ->Demand Manamgement -> Planned independant requirements -> Planning strategy -> Assign MRP group to strategy group (t.code OPPU).Here the startegy group is assigned to the plant+MRP group. In the previous step of the path Define strategy group, different planning strategy can be assigned to strategy group. And in define strategy step, the requirement types are assigned.so depending on material master MRP group and strategy group, the requirement types are derived.

Regards,

Former Member
0 Kudos

Thanks Shiva for your help.

Regards,

Nitin

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Check in OPPQ whether the status of all tabs are "Maintained".