on 11-14-2011 12:13 PM
Hi Experts,
i am experiencing error in cproject preliminary costing. please refer below error.
i have the choosed the costing variant as ad hoc cost estimation in controlling for easy cost planning. i need to create a quotation from cproject.
Please sugeest me what is missing?
thanks in advance,
Prabu
-
Error occurred in accounting - check the costing in the ERP system
Message no. DPR_FIN_GECCO026
Diagnosis
Errors occurred in costing in the ERP system.
Procedure
Check the costing log for costing in the ERP system:
Call costing:
If it is preliminary costing, the hyperlink for calling the ad hoc cost estimate can be found in the Costing view.
If it is costing for an account assignment object (after transfer), the hyperlink for calling Easy Cost Planning can be found in the Services view.
In costing, choose Revaluate All Items. The costing log is then generated with the error messages.
Procedure for System Administration
This message has the number DPR_FIN_GECCO026.
Hi Prabu,
Set a breakpoint in class CL_DPR_FIN_GECCO_CALCULATION and method CALCULATE and check in the debugger which internal errors are given.
Regards,
Brendan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prabu,
Check for more detailed error messages in transaction COCPCPR on ERP system?
Regards,
Brendan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
7 | |
3 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.