Transfer of Time Recorded does not post actual cost to Project

Former Member
0 Kudos

Hello. I am having a bit of a problem. Before now, after transferring recorded time to network activity, the actuals were posted and displayed in the Plan/Actual/Variance report but for some reason, when I transfer recorded time now and run the report, no actual is recorded. Any idea what may have caused this change?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

The unit of the activity type was changed to DAY but time recording was in Hours. After changing the UoM of the activity type to hours, actuals were posted.

pradeep_mahamuni
Contributor
0 Kudos

hi,

Check for the period and year you postd the actual time you have planned the price for your activity type in KP26.

regards,