Limit of activities in cProject module

Former Member
0 Kudos

Hi,

Is there any limit in the number of activities that can be ceated inside a project in cProject module?

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Jorge,

There's no technical restriction, BUT SAP recommends not to exceed 1000 project elements per project in order to guarantee good response time.

A project element can be: phases, tasks, (mirror tasks must be counted twice) checklist items, roles, resources and so on.

Please check SAP Note: 756670.

BR

Matthias

Former Member
0 Kudos

Matthias, Thanks for the answer.

Is it any possible workaround to solve it?

Have anyone found the same problem? Is the performance really affected in a high level?

Thanks,

Former Member
0 Kudos

Hi,

My main customer is facing right now huge problems of performance due to big projects with more than 2000 elements.

So it is crucial during your prototype phase to simulate one project close to the major ones that could be run by your end-users, in order to confirm the response time.

BR

Matthias