Hi all,

I have a following situation. My client has one planning area and one MPOS set up for DP and this is for the process in one country. We have the next release for another country and we are deciding on whether to use the same PA or create another one. How will both the options impact the performance?

Any urgent reply is greatly appreciated

Sai

Former Member
replied

Hi Sai,

2] Check at what level Planning of SKU will be done for what duration. The performance of SAP APO planning books reduces drastically if there are more than 30,000 cells at any point.

Here 30,000 cells means I can have say 500 KF's to be displayed for say 60 Months [Considering data is stored on Monthly buckets] in Data View.

Else it can also be say I have 500 Product SKU's for which I need to display Sales History of last 5 Years.

If Data view have to display data for more than 30,000 cells than it will be drastically slow.

Hope this make you clear.

Regards,

Sameer