cancel
Showing results for 
Search instead for 
Did you mean: 

Stability test...

Former Member
0 Kudos

Dear ALL,

We are going to implement stability study , we have done configuration , now when I am creatinf notification with material and in that while creating initail sample system shows me Error "the function you selected can n't be carried out ".

When I checked the detail info i got the system status OSNO outstanding notification"and status no- ACTV stability study Active.

I have checkd stutus profile which same exactly as we have in development server ( in development server I am not getting this error)

Stutus profile's all indicators are same as dev server.

Pl. guide me to come out from this issue.

Regards,

Prerna Verma

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

first u save it and than through QM02 open it , and change the user status as ACTIVE

bcoz without activating this sytem not allowed the next object.

User status will be ACTV CRIS

and system allows you to create the initial sample from ur action box

Regards

Shailendra gaur

SAP-QM

Edited by: D GURU on Nov 10, 2011 12:33 PM

Edited by: D GURU on Nov 10, 2011 12:34 PM