I found a wierd scenario for my project. I have defined 3 years budget (year 2010, 2011 and 2012) in the project. But somehow I cannot view/see the budget for year 2010. I did check SAP table BPJA, budget for year 2010 is still in the table, then why is it not shown in CJ33 or CJ32? the overall value is including budget year 2010, but i cannot view the details for year 2010.

Please advice.

Thank you.

Regards,

LL

Accepted Solutions (1)

Accepted Solutions (1)

former_member388328
Active Contributor
0 Kudos

Hi

Check ops9 budget profile, if past field is 0 then change it.

Thanking you

Vengaiah Chowdary

Answers (1)

Answers (1)

gerry_hodgins
Active Participant
0 Kudos

Hello LL

I think this is a question for financial control thread

but, In CJ33 the tables containing the information fiscal

year and period and costs are table COSP and COSS

Depending on the parameters in configuration

the current costs could be shown in the period where

they 'should' come up and not in the period where the order was created

maybe note 873977 ( Controlling elements in availability control ) helps?