Hi Experts,
How to get the days view of resource managent(resource/stadding overview) dashboard?
in the standard we only has two views(month & week). i would need to bring days view in the dashboard. units(days) is not meeting my requirements. please suggest how to acheive this
Tthanks in advance,
Prabu
Hi Prabu,
Daily breakdown is not available in PPM standard, but a consulting solution is available.
Please look at the SAP note below if you're interested in:
Note 1246614 - PPM Consulting Solution: Daily Distribution
Regards,
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prabu,
there is no possibility to get a period breakdown of days. You can use "generic intervalls" when you look at single projects. But besides week and month are the only possibilities in PPM
Best regards
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.