MRP based Detailed scheduling

Former Member
0 Kudos

HI All,

I was setting up MRP based Detailed scheduling

FIrst I had activated MRP based detailed scheduling in ERP

then I CIF materials, resources, planned orders & purchase req.

I had verified materials & resources in APO syatem.

Then I could see the orders CIFed to APO in product view.

then I was trying to view the orders in DS board and realise that there is no resource is linked to the orders and cannot view the orders in DS board and not able to do scheduling.

so what should be the solution? Can anybody help me out?

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi Binil.

Please, also check notes

367658 Filtering out operations from orders in CIF

566387 R/3->APO: Activities are missing in the manufacturing order

which provide the most common reasons for missing operations in Planned Orders/Production Orders in APO. Aside from that, you can check if the Delta Report (/SAPAPO/CCR) is able to find these inconsistencies.

Former Member
0 Kudos

Binil,

From your brief description, I belive you have overlooked CIFing over some Master data, either PDS or PPM.

You must create a Production Version in R/3 first. This contains the relationship between material and resource (which is contained in the routing).

For an example of how to set up PP and DS, there re some nice configuration guides in SAP SCM best practices. You will need

Connectivity

http://help.sap.com/bp_scmv250/BBLibrary/HTML/B02_EN_DE.htm

Replication

http://help.sap.com/bp_scmv250/BBLibrary/HTML/B05_EN_DE.htm

Production Planning

http://help.sap.com/bp_scmv250/BBLibrary/HTML/S16_EN_DE.htm

Detailed Scheduling

http://help.sap.com/bp_scmv250/BBLibrary/HTML/S18_EN_DE.htm

Best Regards,

DB49

Former Member
0 Kudos

MRP DS so no source of supply is required in APO!

Check your routing and work center in ECC. The standard value key should be scheduling relevant and generate capacity requirements. The operation duration should be non zero. Resource should be in active integration model.