Production during resource downtime in SNP Distribution Planning Book

0 Kudos

Hi Guys,

We are in SCM7.0. Have got PPDS along with SNP and DP.

When a production order gets its partial confirmation in ECC then the Production (Confirmed) KeyFigure in the SNP Distribution planning book doesnot considers the resource downtimes / weekends. This results in receipts during downtime/weekends in day bucket in the SNP planning book.

Before partial confirmation, the scheduled production orders (in PPDS) is reflected correctly in the day bucket considering the downtimes / weekends.

Any suggestion on relevant Notes / Settings.

Thanks

Srini

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Do you mean SNP creates orders without respecting holidays/downtimes or the orders are displayed in SNP planning book even on holidays/during downtimes?

If it is during display, right click on order KF on the holiday/downtime bucket, choose display details and note order number.

Check in R/3 if order exists for that particular period.

Please note that downtime maintained APO will not prevent display of an existing production order in that bucket.

Regards,

Ashok

0 Kudos

Hi

Thanks for responding.

SNP planning book is reflecting the produciton order under Prod (Confirmed) keyfigure.

Order is created through PPDS in ECC and has been partially confirmed in our scenario.

Before confirmation, the receipts (production order) are shown respecting the week ends and downtime.

But once it gets a partial confirmation the receipts are spread across downtime and weekends in the SNP Planning book.

Former Member
0 Kudos

Hi,

Ok, I understand the issue completely now.

But did you right click on the bucket with downtime in SNP planning book, choose diaply details and see the order details?.

After doing this you can check in product view and MD04 to check if the order is actually open in this period.

If it not open in the period corresponding to the bucket in which it is displayed in planning book and product view and MD04 are fine, Please check this and update, maybe other experts could help.

If you have a really good abapper, you could also debug the planning book load or raise an OSS to be safe.

Regards,

Ashok