Hi Experts,

we schedule data load every month manual, all these days data loads were fine

for VBSAK_DS There is one more additional job runs automatically while the job in process, this starts exactly 2 hrs after we start the manual process, I am not sure why the Job started automatically while job is running.

I could see 2 jobs with VBSAK_DS under data loading/validation and PSA two requests loading. My jobs are terminating in ECC because of the dead locks.

We have not set background schedule for any data loads, this is happening only for VBSAK_DS load.

Appreciate if you can give some inputs to analyze further.

Regards,

Mahesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Mahesh,

One possible reason can be that the timeout time(Scheduler->Timeout time) for your infopackage is set to 2 hours. Because of this after two hours of wait timeout occurs and code triggers a new process for load.

Thanks,

Divyesh

Former Member
0 Kudos

thanks Divyesh,