Reassigning work center for Result Recording or Inspection Lot

jibin_joy
Contributor
0 Kudos

is it possible to change the work center for Result recording or Inspection.....

If possible can u explain how?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Once assigned work center in task list can not be changed dynamically during result recvording !!

Answers (1)

Answers (1)

Former Member
0 Kudos

Can you let us know, why you need to change the work center during the result recording?

jibin_joy
Contributor
0 Kudos

hi

i know that work center is assigned during Inspection planning .....but consider a scenario, if work center which is assigned in Inspection planning is not able to record by some reason. then if user wants to change the work center for further procedures during Result Recording....so is it possible to do so?