Hello friends
We are planning to use strategy 50(MTO) scenario.The material settings for finished product is as below in material master
Procurement-F External
Planned delivery time 20
GR processing time 10.
Sales order created with requested delivery date of 10-Nov-2011.When the MRP is executed it creates a Pur Req with delivery date in past ie on 05/Nov/2011.
My requirment is that the system should consider the planned dlvy time+GR processing time=30 days and the pur req should be created with a delivery date of 10-Dec-2011(ie 30 days from 10-Nov-2011).
What settings needs to be checked the achieve the above result.
Thanks in advance.
Thanks
Harrit
Dear
In Material Master Please Check the Schedule Margin Key
And The repleshment lead Time and also check the Inhouse production
i mean to say is Maintain Floats in the Schedule Margin Key
Go to SPRO >>>Production>>>>Material Requiremet planning >>>>Planning >>>Define Floats
there u can Adjust Floats Accordingt to ur Requirement
With regards
Pushpalas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.