Hi experts,

i want to know the QM cycle. what are the stages involved. can some one help me with the complete overview.(end to end cycle)

Accepted Solutions (0)

Answers (3)

Answers (3)

vasudevap_pushpalas
Active Contributor
0 Kudos

Dear

There are Three Process Majorly involved :

1. Material Incoming Inspection

2. In process Inspection ( During Production inspection )

3.Final Inspection.

Material Incoming : make Inspection Set up and inspection Type 01

Then Create Master Inspection Characters QS21

Then Create Inspection Plan QP01

Then assig Master Inspection in Quality Plan

Then After Go to QA32 Make Usage Desion

here when Raw Material Come to the Inspection Stock u need Clear them by making Desiion

with MVT type 321

2. Inprocess Inspection:

1. 03 inspection type in inspection set up to the material

3.Final inspection : inspection type 04

With regards

pushpalas

Former Member
0 Kudos

Hi,

First of all i would like to strongly suggest/recomment the SAP Notes to go through which i guess can fulfil ur purpose at the best of conceptual levels.

However you can refer to the solution below-

Steps :

1. MM01 : Create Finish material

In QM View in Material Master :

Give Certificate type. QM Control Key and ensure QM Proc. active

Click Insp. setup

Assign insp. Type 04 – GR Insp. for order, by selecting new insp. Types.

Ensure it as active plan, by ticking the active indicator.

2. Goto QS21 , create Master Inspection characteristic

Give Status as Released and Complete copy model for mic

Select Quantitative characteristics and tick the relevant indicators i.e., in this case Lower specific limit, Upper specific limit and Check Target value.

Press Enter

It`ll prompt you for entering lower, upper and target values for the MIC ,

Enter the values.

SAVE

3. GOTO QP01 – Create Inspection Plan with status – Released (4) and Usage – GR (5)

- Click operations, Create Insp. Operation and give the control key as QM01

- Select the inspection operation and click on the insp. Characteristics,

assign the MIC you`ve created and press enter. All the characteristics

will be copied.

4. GOTO QA32 – Inspection lot selection

Give Material and Plant Execute

Select your inspection lot line, and select result recording.

{Incase, if it is not allowed to record results, GOTO QE02, give insp. Lot and select Change Insp. Lot Icon, give the relevant task list usage and press TASK LIST button in the Inspection specification Tab and then SAVE}

Give inspected quantity and target value that is checked

SAVE

You can find in QA32, that the status is changed to INSPECTED

Now again select the insp. Lot in QA32 and goto Usage decision,

Give UD as A – for accept and Quantity to be moved to unrestricted use stock.

SAVE

REFRESH

9. GOTO MMBE

Now you can observe that the stock has moved to Unrestricted use.

Hope it fulfils your purpose at some extent.

Cheers

Chandra

former_member311826
Active Contributor
0 Kudos

Dear Nandi,

There are different type of QM cycle. Mainly following are used. Which process do you want to Know ?

1. Incoming Inspection Process. []

2. Inprocess Inspection. []

3. Outgoing or after Production Inspection.

Regards

Abhijit Gautam

Edited by: Abhijit Gautam on Nov 2, 2011 2:57 PM