Hi APO Experts,
Why are Production Planned in APO CIFfed as Confirmed Planned Orders. As a result, they are CIFfed back to APO as Production Confirmed. Our firm horizon is only one week. But it firms up to 2 months or more.
Regards,
Kat
Hi
Check your Global Parameters and Default Values in the IMG for PP/DS, the tab "ATP Categories" should tell you the ATP category of each of the order types raised by PP/DS planning.
In House Production, planned should be AI
In House Production, Firmed should be AJ
In House Production, Confirmed should be AK
Regards
Ian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Do you see these planned as fixed planned order or you are seeing in "Production confirmed" in Planning book?
PPDS planned order will be visible as Prodction confimed in Plannign book.
Regards,
Vipul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you using Planning Time fence? What about PP/DS Horizon?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.