Production Planned CIF as Confirmed Planned Orders

Former Member
0 Kudos

Hi APO Experts,

Why are Production Planned in APO CIFfed as Confirmed Planned Orders. As a result, they are CIFfed back to APO as Production Confirmed. Our firm horizon is only one week. But it firms up to 2 months or more.

Regards,

Kat

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

Check your Global Parameters and Default Values in the IMG for PP/DS, the tab "ATP Categories" should tell you the ATP category of each of the order types raised by PP/DS planning.

In House Production, planned should be AI

In House Production, Firmed should be AJ

In House Production, Confirmed should be AK

Regards

Ian

Former Member
0 Kudos

Hi,

Do you see these planned as fixed planned order or you are seeing in "Production confirmed" in Planning book?

PPDS planned order will be visible as Prodction confimed in Plannign book.

Regards,

Vipul

Former Member
0 Kudos

Are you using Planning Time fence? What about PP/DS Horizon?