Hello Gurus,
I have question about schedule agreement. I created delivery note and I can see in schedule agreement two schedulle agreement in tree. The second schedule agreement is in document flow depend on the first. In this case my delivery note takes shipto from first Schedule agreement opposite it is wrong. Do you know why are shedule agreement in the tree and why is shipt to on delivery note from first oppposite second?
for understanding please check the link bellow
http://www.filesonic.com/file/2855320095/ScreenHunter_01_Nov._01_11.44.gif
Thanks for your help
Dear Comptom,
If you copying the scheduling agreement from the first agreement to second in that case you need to un check the update document flow in copy controls.
Go to T.code VTAA there select your scheduling agreement at the item level Update document flow un check this and try.
check and revert
Regards
Ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.