How To Update Easy cost planning when cost rates are updated

Former Member
0 Kudos

Hi All,

When Cost rates are updated yearly, how can we update easy cost planning for all existing projects in a go?

For a single project we can open ECP and save. But since we have hundreds of active projects, what is the right way?

I tried BAPI CNECP_MAINTAIN but this has some dependency on Customizing step "Activate Planning on network activities". Since we do not use Networks, this is not activated in our system.

Please suggest.

Remya.

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

Run CJEN for multiple projects as a background job

Former Member
0 Kudos

Hi Virendra,

Thanks for your reply.

It didnt work for me. I still see the old rates after executing CJEN.

They do change when I go to Easy cost planning and click on "Re-evaluate".

Best regards,

Remya.

Former Member
0 Kudos

Solved using DPR_EVE_BATCH_DPO with 'Use Customizing' checked.