When trying to put a final confirmation on all activities of a project in CN47, I am getting this error:

03.05.2007 is before validity period of factory calendar, check date

Factory calendar for is valid from 2008 - 2020.

How can we fix this ?

Regards

Gaurav

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

Changed the dates and resolved the issue

Former Member
0 Kudos

Hi Gaurav,

03.05.2007 is before validity period of factory calendar, check date

Factory calendar for is valid from 2008 - 2020.

The answer to this issue lies in the statments posted above. Check it and maintain a proper validity date for the calendar or shift the dates of the activitiy.

Regards,

Gokul

Former Member
0 Kudos

Gaurav,

Check the planned dates for all the activities that you are trying to confirm is lying within the valid calender. Since the system is prompting the date 03.05.2007.

rgds

MohanDesai
Active Participant
0 Kudos

Hi,

Use OP03 or SCAL and set the validity period of Factory Calendar.

Mohan R. Desai

Former Member
0 Kudos

Hi

Check any of your activity dates falls in to that period?. If so correct it and confirm again.

Regards,

PSR

Brendan_Ward
Advisor
Advisor
0 Kudos

Hi,

Run ZCATS_CONF from SAP Note 505134 to check for any inconsistencies. If any exist, create a message for SAP Support with the details.

Regards,