External requirements from ERP to SRM with ExtendedClassic scenario for PPS

Former Member
0 Kudos

Hi all,

We are having SRM 7.01 system with ERP ehp4, and we have to do PPS ( Public sector Procurement) as part of our implementation,for that we need to activate Extended classic Scenario.

My question is whether we can have external requirements ( Material PR and Service PR) from ERP can be processed in the srm system.

Please help.

Regards,

Raju

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi raju,

You can transfer PR from ERP to SRM sourcing cockpit, only requirement is you need the materials replicated from ERP to SRM.

Regards

Sam

Former Member
0 Kudos

Hi Sam,

Whether PI/XI integration is required for this?. If its not there , how can we goahead?.

Thanks,

Raju

Former Member
0 Kudos

Hi

We can use either the CPPR functionality which requires PI/XI to be in place or maintaining the T160PR and T160EX tables in ECC and running the report BBP_EXTREQ_TRANSFER to push the PR's into SRM. In SRM we have to maintain the entry channel to bring the PR's into SOCO.

R/ Reddy.

former_member22425
Active Participant
0 Kudos

Hello Raju,

To make use of the CPPR functionality follow the SAP Note 1263876 to do the Configuration of Procure-to-Pay Scenario.

Maintaining the T160PR and T160EX tables in ECC and running the report BBP_EXTREQ_TRANSFER to push the PR's into SRM is obsolete from SRM 70 onward's.

Best Regards,

Rahul