Hello,

We loaded supplier(LSUPPLIER) from ECC to SPM. The data got loaded to PSA and info objects. But when I release the supplier load, the process chain is running for last 7 hours.

We had same issue in QA where it ran for almot 2 days and even after 2 days it did not finish - in fact there was no progress as well. When I checked in SM50, there was a process with sequential read on /BI0/PXALOCSUPP for almost 2 days.

Has anyone faced similar issue and any pointers for this issue?

Regards,

Prasanna

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

WE have seen this happen if too many of local supplier point to the same cleansed supplier(generally a dummy cleansed supplier). Is that the case for you.