cancel
Showing results for 
Search instead for 
Did you mean: 

Saving SAP jobs and spool for reorg jobs

Former Member
0 Kudos

Hi,

we are in process of archiving now, Functional team request to keep the jobs and spool of that archiving background jobs from reorg .

I am not able to find any option to keep the jobs and spool from reorg jobs...

Please suggest...

Thanks,

Subhash.G

Accepted Solutions (0)

Answers (2)

Answers (2)

JPReyes
Active Contributor
0 Kudos

As far as using the standard tools, you'll need to stop RSBTCDEL2 and RSPO1041 from running or extend the age of deletion

Regards

Juan

Former Member
0 Kudos

Hi,

I got the solution for this.

While scheduling the sap reorg jobs there is a filed called " username" normally it will be * , in my scenario i have given the background user name so that the reorg job removes the old jobs of that user only.

I am scheduling the jobs with my id which will not be part of reorg user.

Thanks,

Subhash.G

Former Member
0 Kudos

Hi Subhash,

I think you can create a customize variants from the standard variants and define in the step of job and spool reorgs background jobs. The customized variant must be created in such a way that the archiving jobs/logs should be excluded from the reorg.

I never tried this. Please work with your ABAP team.

Thanks,

Siva Kumar