Good afternoon, first of all thank you very much for the support they can provide. I have developed a JDBC interface -> BPM (Multimapping) which works well. Modify a Message Mapping in the BPM that I use for an RFC Lookup, I have added the Configurable Parameters in the BPM and Integration Directory and everything works fine at design time. But when running the interface at run time the message reaches the BPM and the error "error in BPE inbound Permanent processing".

I have reviewed the Business Process Engine in the RWB and the item is Red Schedule Background Job for Reorganization and detail reads: "Background Job for Reorganization = Not Scheduled".

As I can solve this problem. Thank you very much.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

Please go to trx SWF_XI_CUSTOMIZING and check if all nodes are green.

You can run the Automatic Customizing there to schedule the job for reorganization.

Kind regards,

Sarah

Former Member
0 Kudos

Hi Sarah, thanks.