Hi experts,

We are using Easy Cost Planning (ECP) and we would like to know if it is possible to have the planned price copied to the purchase order document (or purchase requisition) created through Execution Services.

We do not want to have a new price determination in the document.

Is it possible?

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

fortian
Active Contributor
0 Kudos

Thanks phoenixcfa.

We won't do it for now but is good to know.

fortian
Active Contributor
0 Kudos

Does anybody know a BADI or USER-Exit to use in order to accomplish this requirement?

Thanks

Former Member
0 Kudos

Similar function was implemented for our company using Exits/BAPI for PR price. Was done by MM team. They achieved it through field exit on PRICE field within the network.

Hope this could help.