Hi Masters,

We have a Requirement in Which the client wants that while Creating Delivery Document through VL01N the Actual PGI Date Entered should not be before the Panned GI Date it should be only After the Planned GI Date. If the user Tries to Enter the Actual GI Date which is before the Planned GI Date the System should not Accept it and should give and Error.Please tell how to Configure this.

Thanks in Advance.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

For this you have to go for enhancement.you can use this user exit. MV50AFZ1

Thank you.

Former Member
0 Kudos

Hi,

Pls make use of Status profile for the user as well as maintain proper schedule lines