Hi,

I have a basic question on an SNP Functionality.

SNP prdn horizon during which no new orders are created.

For example:

I am running SNP Plng engine with planning horizon from today. The prdn horizon is 15 days and the reqt is on 10th day.

The processing time is 7 days. Today is 05.10.2011 and so the prdn hor w

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

SNP production horizon functionality:

SNP does not create any palnned order in SNP production horizon it moves planned orders to first day after this horizon.

In your exmaple planned order should be created on 01-11-2011 (assuming 5 days working,holiday on saturday and sunday).

Regards,

Nikhil

Former Member
0 Kudos

It s clar to me now. This thread can be closed

Regards,

SS

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

Please check if you have available capacity within the 15 days horizon...