on 10-20-2011 4:17 PM
Hi,
we upgraded our Solution Manager 7.0 EHP1 development system to 7.1 SPS3 (including all new sap notes).
During solman_setup we get the following error at -> System Preparation -> 6 Prepare Landscape -> 6.4 Set up LMDB:
No such namespace: "active"
Due to this error it is not possible to add a synchronization connection between our local SLD and LMDB, because there's no target namespace!
Does anyone know how to add the namespace "active" ??
Greetz
André Richter
Make sure that your SLD meet the requirements:
SAP NetWeaver Release
The following table gives an overview of the SAP NetWeaver versions for an LMDB-compatible SLD, and whether, and since when (which support package stack), an SLD satisfies the minimum requirements for LMDB:
SAP NetWeaver Release (SLD)
Supported Support Package Stack Level
SAP NetWeaver 6.40
not supported
SAP NetWeaver 7.0
not supported
EHP1 for SAP NetWeaver 7.0
not supported
EHP2 for SAP NetWeaver 7.0
SP6, patch 5
SAP NetWeaver 7.1
SP9
EHP1 for SAP NetWeaver 7.1
all SPs
SAP NetWeaver 7.2
all SPs
SAP NetWeaver 7.3
all SPs
If you cannot give your central SLD a required status, you can use another SLD which does satisfy the minimum requirements (e.g. the SAP Solution Manager SLD), and fill it with the data from your central SLD, using SLD bridge functionality.
Model and CR Content
The CIM model and SAP CR content requirements are:
CIM model 1.6.16 or higher
Newest SAP CR CONTENT, at least version 7.0
For more information about updating CR content, see SAP Note 669669.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
78 | |
10 | |
9 | |
7 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.