budget in PS module

Former Member
0 Kudos

Hi Experts,

Budget Error Detail

a) System should allow release of Partial budget ie less than planned cost.

b) System gives error while converting PR into PO ( Non-modvatable tax codes) ie system is considering Gross Amount ( ie commitment + taxes)

while converting PR intoPO , which exceeds the budget and gives error.whereas in PR , only commitment value is considered wrt budget and hence no error.

ie some Tax Codes are : CA, CB, EB, ED ET, EU,VV etc.

Requirement :- System should not give error while converting PR into PO.

plan budget committment

1000 1000 1000

while converting pr into po system gives an error i.e network act exceeded budget....

Please suggest..

thanks

pkg

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

I dnt knw why u have maintain 0 % as usage in budget profile.

Regards

Keshav

Edited by: keshav619 on Nov 10, 2011 6:35 AM

Former Member
0 Kudos
System should allow release of Partial budget ie less than planned cost.

Possible to release partially.

Requirement :- System should not give error while converting PR into PO.

Try exempting those tax related cost elements from budget check.

Former Member
0 Kudos

Thanks Ravi,

As you said partial release is possible, but i am getting an error it says" Item WBS element NTD-0001060 budget exceeded

Message no. BP603"

it is not allowing me to do the partial release of budget.

in the budget profile followig have been maintained.

availibilty control-

act type 1, usage -0.00

overall -yes

releases -yes

object currency - yes

please advise that do i need to make any changes.

thanks

Prashant

Former Member
0 Kudos

Dear Ravi,

I checked those tax code's cost elements. Interestingly these tax are not assigned to cost elements. these are no modvat tax codes. Please suggest. How to get these cost elements...whether they are maintained anywhere else and also let me know if we have any other solution for this.

Prashant

Former Member
0 Kudos

Hi

What is the reason for choosing 'object currency" other than Controlling area currency.

Hope you have common currency across Contorlling area, Company code and object currency

Regards,

PSR