Return delivery to project stock

0 Kudos

Hi

Is it possible, that when we do PGR against return delivery in SD, the stock directly goes to the project stock rather going to retrun stock. WBS element is mentioned in the Sales order against which delivery is getting created.

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi

Thanks for your inputs.

But i am looking for the movement type which will bring the material directly into the project stock once PGR is done.

i am aware of the movement type used for transfering of goods from return stock to project stock.

Thanks

fortian
Active Contributor
0 Kudos

Did you solve it?

Former Member
0 Kudos

Make sure that the sales order item- and schedule line category is assigned to project stock (account assignment category in VOV6 and VOV7).

It might also be necessary to make "Project" optional in the account assignment and transfer posting sections for the movement (OMJJ - Field selections).

former_member134435
Participant
0 Kudos

Hi,

Please tell me the process of transferring stock from a return to project stock directly and which mvt I can use for this.

Thanks

Former Member
0 Kudos

Hi ,

you have to search in OMJJ wich movement type can return stock to project stock and use it for your return.