Scheduling among networks

Former Member
0 Kudos

Hi Experts,

I encountered 1 problem when I do the scheduling among networks. Please help:

- I have 2 different networks:

+ Network 1: Activity 1 --> Activity 2 ( Relationship FS)

+ Network 2: Activity 3 --> Activity 4 (Relationship FS)

+ I create 1 more relationship FS between: Activity 2 --> Activity 3.

When I do the partial confirmation for activity 1, and reschedule the project, only scheduled date of network 1 is rescheduled, it doesn't reschedule network 2 (as I expect).

Could you please give a solution for this case.

Thanks a lot,

Khoa Huynh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi ,

Which scheduling method your using,Dependence on scheduling method (Forward or Backward)you need to change the second network starting date or end date .then you can go for scheduling.

Regards

R.B.Rao

Former Member
0 Kudos

Hi bhavanio rao,

I use the forward scheduling.

For sure that if I change the start date of the second network, I can go for scheduling.

But I don't want that, I expect the system will reschedule automatically the second network when I change the actual date of activities in network 1 (because there is a FS relationship between network 1 and 2)

Regards,

Khoa Huynh

Former Member
0 Kudos

Hi Khoa,

Please check network scheduing parameters in OPU6, particularly Adjust Dates. Check whether system is adjusting basic dates according to operation dates. Also try network scheduling instead of project scheduling in CN24N.

Regards

Shrikant

Former Member
0 Kudos

Hi Experts,

I NEED YOUR HELP ABOUT THIS.

anybody help me?

Thanks and best regards,

Khoa Huynh