on 10-19-2011 5:12 AM
Hi Experts,
I encountered 1 problem when I do the scheduling among networks. Please help:
- I have 2 different networks:
+ Network 1: Activity 1 --> Activity 2 ( Relationship FS)
+ Network 2: Activity 3 --> Activity 4 (Relationship FS)
+ I create 1 more relationship FS between: Activity 2 --> Activity 3.
When I do the partial confirmation for activity 1, and reschedule the project, only scheduled date of network 1 is rescheduled, it doesn't reschedule network 2 (as I expect).
Could you please give a solution for this case.
Thanks a lot,
Khoa Huynh
Hi ,
Which scheduling method your using,Dependence on scheduling method (Forward or Backward)you need to change the second network starting date or end date .then you can go for scheduling.
Regards
R.B.Rao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi bhavanio rao,
I use the forward scheduling.
For sure that if I change the start date of the second network, I can go for scheduling.
But I don't want that, I expect the system will reschedule automatically the second network when I change the actual date of activities in network 1 (because there is a FS relationship between network 1 and 2)
Regards,
Khoa Huynh