Error during PGI VL02N

Former Member
0 Kudos

Internal error in LMLCCS_UPDATEF02 LCL_DB method get_normvector position A with RC 1

Message no. MLCCS009

at the Time of PGI (VL02N)

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Sudip

The reason is that ML has started production again after configuration changes caused by the cost component split.

The solution: The error reported may be because of the fact that you have activated the actual cost component split in Customizing after the production startup.

Please refer the OSS notes "Note 639675 - Initialization of the actual cost component split".

May be helpful.

Regards

Hrishikesh

Answers (3)

Answers (3)

Shiva_Ram
Active Contributor
0 Kudos

Check OSS Note 323386 - Error message MLCCS009 in program SAPLMLCCS_UPDATE

Also check OSS Note 750107 - Error MLCCS009 for stock transfer

Regards,

Edited by: Shiva Ram on Oct 18, 2011 7:02 AM

Lakshmipathi
Active Contributor
0 Kudos

You can also have a look at the following note:-

Note 323386 - Error message MLCCS009 in program SAPLMLCCS_UPDATE

G. Lakshmipathi

jignesh_mehta3
Active Contributor
0 Kudos

Hello,

Check the below thread:

The above is the only thread available on SDN for your error (message no. MLCCS009).

Hope this helps,

Thanks,