CIF transfer of Planned Independent requirements

Former Member
0 Kudos

Hi Friends,

We want to transfer Planned Independent requirements from ECC to APO through CIF.

Planner maintained the PIRs in Monthly periods. and CIF transfer happening successfully.

However the Requirement date in APO product view showing as starting of the Month.

For example:

Forecasts maintained in ECC :

M1- 2011 -


10000

M2- 2011----- 12000

When comes to APO Forecast requirement date/time set as:

Req Date--


Time----Qty

01.01.2011---03:00----10000

01.02.2011---03:00----12000

but we want requirement date and time to be set to month end dates (want to see as below)

Req Date--


Time--


Qty

31.01.2011------12:00 -


10000

28.02.2011----12:00-----12000

Can you please provide some useful hints on how to acheive this.

Best Regards,

Krish

Edited by: Tho Krish on Oct 18, 2011 9:57 AM

Edited by: Tho Krish on Oct 18, 2011 9:58 AM

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

You need to use User Exit i.e CIFPIR02 on ECC side to convert the month into last day

Former Member
0 Kudos

Hi,

Have you checked in ECC MD04 tcode. What is the date it is showing there?

If in MD04 date of ind. requirement is showing same as APO then there is no problem it is expected behaviour.

If not Try running CCR to correct inconsistency.