Hi,
While creating the quotation we want that availibility check should not be carried out when user enter the material code on VA21 screen, as per the material lead time system should directly set the delivery schdule date, as in many cases if some other user is working on the same material then system save the quotation with confiirm quanity as zero in the schdule line, thsi we want for only one lant. what setting can be made for this.
regards,
zafar
HI,
If you dont want to carry out the availability check at quotation level just remove the availability check mark in schedule line level of particular quotation t.code vov6.