Dear Experts,
We have noticed a problem with tolerances not being replicated to ECC. Upon creation of a PO(with reference to a SHC with a contract) in SRM, the over and under delivery tolerances set in the contract are copied in the SRM PO. Once the PO is replicated in backend, these tolerances are 0% in the backend PO. How can this be corrected - to replicate the same tolerances in ERP?
We are in ECS, SRM 7.0 and ECC 6.0.
Thanks,
pipsquik
Hi,
SRM and ECC (BE) tolerances must be configured separately and all limits are applied in system independently.