on 10-13-2011 11:59 PM
Hi everyone!
We are implementing OpenPS in our customer. We had no problems with the
download from PS to MS Project. But we had some issues with the upload.
We made many changes and tried many times, and finally could make the upload
work. But there are many prerequisites we had to fulfill, that we cannot
follow here.
Specifically, we had to:
1) Set the fields Responsible and Profit center as non mandatory (we had them as mandatory, and the upload didn't work)
2) In the project profile, we had to enter a default plant (our project profiles are corporative, so they are not country-specific. Therefore, we cannot set a default plant).
Is there any way the upload can work without this? I mean, without having to set the fields Profit center and Responsible person as optional, and without having to enter a default plant at project profile level.
I would really appreciate your help in this point!
Regards!
Hello
Are you using the 'Retain in PS' field?
Can you please review point 34 from note 579761.
The OpenPS interface translates a valid combination of plant
and work center into a resource in MSP and viceversa. Therefore your
system is working as designed.
The interface accepts plant/work center or plant/work center/activity
type combinations or a personnel number as a resource.
It is necessary that these (plant, work center, activity type, personnel
number) information already exist in the R/3 system.
Please note also that:
"The personnel resources assigned to the task are created as activity
elements and the work on the resource is assigned to the activity
elements." (from documentation)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.