Cost Element not showing against material in ECP

Former Member
0 Kudos

Team,

In Easy Cost Planning I need to get the cost element by default against the material once we confirm the template. Where I need to define this.

Material is created using MM01 and Cost Template is created using CKCM

Reg/ Tony

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

It is defined in the material master data.

Regards,

Ammar

Former Member
0 Kudos

Thanks, but can you pl help me with more info like where and how its defined

Former Member
0 Kudos

In material master you maintain the valuation class (accounting 1 tab). In configuration (TCode OBYC) you maintain the account assignment for the valuation class. There are more parameters you need to consider before make the configuration changes. I would suggest you to discuss this with your MM consultant, or lookup this option on the relevant forum.

Regards,

Ammar